Data Centers Were Responsible For 46% Of PJM's Last Four Capacity Auction Costs

ZeroHedge
Published
Data Centers Were Responsible For 46% Of PJM's Last Four Capacity Auction Costs

The short version

  • Monitoring Analytics is the grid operator’s independent market monitor.
  • In PJM’s last four base capacity auctions, data center-driven capacity charges totaled $29.4 billion — 46% of the $63.6 billion in total capacity charges in that period…
  • Monitoring Analytics plans to publish its analysis of the most recent auction in a few weeks, he said.
  • PJM’s capacity auctions and the price of electricity has become a major political issue in the grid operator’s footprint…
  • In September, governors from PJM states formed a collaborative to advocate for their interests with the grid operator.

The story

Data Centers Were Responsible For 46% Of PJM's Last Four Capacity Auction Costs

By Ethan Howland of UtilityDive

Data centers are responsible for $6.3 billion, or 38%, of the $16.4 billion in charges from the PJM Interconnection’s just-held capacity auction, Joseph Bowring, president of Monitoring Analytics, said in an email to Utility Dive. Monitoring Analytics is the grid operator’s independent market monitor.

In PJM’s last four base capacity auctions, data center-driven capacity charges totaled $29.4 billion — 46% of the $63.6 billion in total capacity charges in that period, Bowring said. Monitoring Analytics plans to publish its analysis of the most recent auction in a few weeks, he said.

PJM isn’t fully grappling with the ramifications of data center development, according to Bowring. “PJM is continuing to act like it’s business as usual,” he said in an interview on Friday. “You have to open your eyes and recognize that it is really a paradigm shift, and failing to do that imposes costs on other customers.”

Ratepayers in PJM are not only paying capacity charges for existing and potential data centers, they are paying for higher energy and transmission costs data centers have caused, according to Bowring.

PJM’s capacity auctions and the price of electricity has become a major political issue in the grid operator’s footprint, which includes 13 Mid-Atlantic and Midwestern states and the District of Columbia. In September, governors from PJM states formed a collaborative to advocate for their interests with the grid operator.

On March 4, Google, Meta, Microsoft and other data center companies pledged at the White House that they would protect consumers from price hikes due to data center energy and infrastructure requirements.

However, meeting that pledge is impossible in PJM under its current rules, according to Bowring.

“There’s only one way to do what hyperscalers agree is the right thing to do, and that is to run a separate auction,” Bowring said. “That’s good for the hyperscalers … because it allows them to get capacity and be served reliably, and it’s good for other customers because it separates out the impact from the data center.”

First, data centers and other large loads should contract for their own generation, according to a proposal the market monitor made last month as part of PJM’s fast-track stakeholder process for a backstop reliability auction. For those that can’t bring their own generation, PJM should hold separate auctions to procure their capacity supplies under 15-year contracts, Bowring said.

PJM buys capacity ahead of time — normally three years in advance — based on its demand forecast. However, it is unclear exactly how much data center load will materialize, adding uncertainty to the forecast.

While PJM has tried to make its data center forecasts more accurate, there is growing opposition to data centers across the United States, with some major projects getting canceled, Morningstar DBRS said in a report released Monday.

“As states consider new taxes, restrictions, and moratoriums on data center growth, escalating stakeholder opposition could become a material credit factor, potentially weakening data center project credit quality by reducing development visibility, increasing regulatory risk, and challenging assumptions around the pace and certainty of future AI-driven capacity expansion,” the credit ratings agency said.

Under Monitoring Analytics’ auction proposal, removing data centers — and the uncertainty around their future loads — from the base capacity auction ensures ratepayers won’t pay for unneeded capacity.

PJM’s board is developing a backstop auction proposal for data centers that it aims to file with the Federal Energy Regulatory Commission this month so the auction can take place in September.

Under a plan that received the most support in the stakeholder process, utilities and other load-serving entities, and potentially data centers themselves, would ask PJM to buy a specific amount of capacity in a one-time auction. PJM staff proposed that it would procure in a one-time auction the shortfall from its last base capacity auction — about 6.8 GW.

Tyler Durden Tue, 07/21/2026 - 22:35
Read the full story at ZeroHedgeOriginal

Related Markets

All Markets
View full chart →
View Full Chart
View full chart →
View Full Chart

Market data may be delayed. Not financial advice.

How this story developed

Full timeline

Alto has tracked this across 3 days of coverage from 1 outlet.

    • Data Centers Were Responsible For 46% Of PJM's Last Four Capacity Auction CostsYou are here

Powered by Gab AI

The Story At A Glance

Reading this article now — analysis appears below

Reading the article

💡 AI analysis provides alternative perspectives on current events

Up next

Related coverage from across the outlets Alto indexes.

Questions Alto can answer

From this story — each link opens a live data page or a tool already filled in.

  1. What does gas cost in District of Columbia right now?Current statewide average
  2. How does District of Columbia rank on taxes and cost of living?Taxes, wages, cost of living
  3. What were the latest District of Columbia lottery numbers?Recent winning numbers
  4. Who represents District of Columbia in Congress?House and Senate members
  5. What are District of Columbia's voter ID rules?ID rules and deadlines
  6. What is $100 from 1990 worth today?CPI-adjusted dollars — result on the next page
  7. Where does $75,000 rank in District of Columbia?Census percentile — national and state
  8. What federal tax bracket is $80,000 (single)?Marginal and effective rate on the next page
  9. What's Alto covering on the Finance desk?Latest headlines on this beat
  10. What else is Alto tracking on Federal Reserve & Interest Rates?Topic hub with related coverage
  11. What else is Alto tracking on Inflation?Topic hub with related coverage

All toolsAll topicsSource directoryStory timelinesHeadline comparisonSearchMost read

From Gab Shop

Official merchandise. Every order funds free speech infrastructure.

Shop all products

Install Alto on your phone

Add Alto to your home screen for breaking news — no app store, no account.

  1. Step 1Open alto.gab.com in SafariMust be Safari — not Chrome or in-app browsers
  2. Step 2Tap the Share buttonSquare with an arrow, at the bottom of Safari
  3. Step 3Tap "More"If you don’t see Add to Home Screen yet
  4. Step 4Tap "Add to Home Screen"Scroll the share sheet if you need to
  5. Step 5Tap "Add"Alto appears on your home screen like any other app.
gab

Talk Markets Freely

Trade ideas, earnings, and the Fed with investors who aren't waiting on a moderator's approval.

What Makes Gab Different

We're not just another social network. We're a platform built on principles that matter.

Freedom of Speech & Reach

All First Amendment protected speech is welcome. No algorithmic throttling or shadow banning.

Family-Friendly Platform

We maintain a clean environment. Explicit adult content is strictly prohibited.

Western Nations Only

Third-world IPs are blocked. No scammers, no spam farms. Built for Western civilization.

Funded By Users

Our users are our investors and customers. You're not the product being sold.

Battle Tested

A decade of standing strong. Banned from app stores, banks—and still here.

American Owned & Operated

We reject foreign censorship demands. Built by Americans, for free people.

Support Alto & Gab

Alto is funded entirely by readers like you. Your donation helps us continue delivering curated news from a right-wing Christian Nationalist perspective, powered by Gab AI.