Second Largest US Grid Operator Proposes Reliability Rules For Data Centers

ZeroHedge
Published
Second Largest US Grid Operator Proposes Reliability Rules For Data Centers

The short version

  • The proposal is a part of MISO’s response to FERC’s mid-June “show cause” orders requiring major grid operators to set rules that meet certain criteria for adding data centers and…
  • MISO said it plans to make additional proposals by a Nov. 16 deadline.
  • On average, electric demand was relatively flat between 2009 and 2024, growing by about 0.5% a year, MISO told FERC.
  • Now, the grid operator expects 1% to 2% annual growth through 2044, with higher growth rates in the near term, according to MISO…
  • MISO’s proposal defines “large loads” as those larger than 50 MW, and “computational loads” as large loads that include at least 25 MW of demand from information technology…

The story

Second Largest US Grid Operator Proposes Reliability Rules For Data Centers

By Ethan Howland of UtilityDive

The Midcontinent Independent System Operator - the second largest US grid operator after PJM Interconnection - on Friday proposed a set of requirements large loads must meet before they can connect to the grid, including ramping and ride-through specifications.

The “interconnection reliability requirements” framework aims to improve MISO’s visibility into large load “characteristics and behavior, support reliable planning and operational decision-making, and establish scalable and technically justified expectations proportional to demonstrated reliability risk,” the grid operator said in its filing with the Federal Energy Regulatory Commission.

The proposal is a part of MISO’s response to FERC’s mid-June “show cause” orders requiring major grid operators to set rules that meet certain criteria for adding data centers and other large loads to the grid. MISO said it plans to make additional proposals by a Nov. 16 deadline.

MISO’s proposal follows similar actions at the Electric Reliability Council of Texas and the PJM Interconnection aimed at setting reliability standards for large loads after several incidents where data centers suddenly tripped offline, raising concerns about grid stability.

On average, electric demand was relatively flat between 2009 and 2024, growing by about 0.5% a year, MISO told FERC. Now, the grid operator expects 1% to 2% annual growth through 2044, with higher growth rates in the near term, according to MISO, which runs the grid and wholesale power markets from Louisiana to Minnesota.

MISO’s proposal defines “large loads” as those larger than 50 MW, and “computational loads” as large loads that include at least 25 MW of demand from information technology equipment, such as servers, storage and networking hardware.

The separate computational load classification will allow MISO to target certain requirements just to data centers, the grid operator said.

“Computational loads may exhibit rapid and coordinated changes in demand, significant power-electronic behavior, and distinct responses to transmission system disturbances,” MISO said.

MISO’s proposed reliability framework sets requirements for its transmission customers that take service on behalf of large loads. It covers four main areas:

  • Visibility requirements

To improve MISO’s visibility into large loads on its system, transmission customers must provide MISO with basic information and modeling data on large load facilities, according to the proposal. They must also provide real-time and day-ahead load forecasts for the facilities.

The information is needed “to support planning studies, operational assessments, and accurate representation of large loads behavior and system impacts,” MISO said.

  • Phasor Measurement Unit requirements

The PMU requirements set monitoring expectations for computation loads through high-resolution, time-synchronized measurements, according to MISO.

“PMU data provides MISO with greater visibility into facility behavior during system disturbances and rapid operating changes, supporting model validation, performance verification, disturbance analysis, and identification of potential dynamic interactions with the transmission system,” MISO said. 

  • Ramp requirements

MISO said its proposed ramp requirements address the rate at which computational loads may increase or decrease electric use during stable-state transitions. 

“Managing rapid changes in demand helps reduce real-time supply-demand imbalances, sudden change in transmission power flows, and associated operational impacts, while supporting more reliable system operation,” MISO said.

  • Ride-through requirements

The proposed measures set minimum disturbance performance requirements for computational loads during voltage and frequency disturbances to reduce the risk of unnecessary disconnection or customer-initiated rapid reductions in demands during system events, MISO said. 

MISO’s proposal includes grandfathering provisions to provide certainty to existing and nearly complete commercial arrangements for large loads. MISO asked FERC to let its proposal take effect on Dec. 4.

MISO plans to file additional large load-related proposals, including for additional transmission products and associated study processes, protections against cost shifts and the treatment of generation service to “electrically proximate” large loads, MISO said.

Tyler Durden Wed, 09/02/2026 - 11:00
Read the full story at ZeroHedgeOriginal

Related Markets

All Markets
View full chart →
View Full Chart
View full chart →
View Full Chart
View full chart →
View Full Chart

Market data may be delayed. Not financial advice.

Powered by Gab AI

The Story At A Glance

Reading this article now — analysis appears below

Reading the article

💡 AI analysis provides alternative perspectives on current events

More to read

Recent stories from across the outlets Alto indexes.

Questions Alto can answer

From this story — each link opens a live data page or a tool already filled in.

  1. What does gas cost in Texas right now?Current statewide average
  2. How does Texas rank on taxes and cost of living?Taxes, wages, cost of living
  3. What were the latest Texas lottery numbers?Recent winning numbers
  4. Who represents Texas in Congress?House and Senate members
  5. What are Texas's voter ID rules?ID rules and deadlines
  6. What is $100 from 1990 worth today?CPI-adjusted dollars — result on the next page
  7. Where does $75,000 rank in Texas?Census percentile — national and state
  8. What federal tax bracket is $80,000 (single)?Marginal and effective rate on the next page
  9. What's Alto covering on the Finance desk?Latest headlines on this beat
  10. What else is Alto tracking on Federal Reserve & Interest Rates?Topic hub with related coverage
  11. What else is Alto tracking on Inflation?Topic hub with related coverage

All toolsAll topicsSource directoryStory timelinesHeadline comparisonSearchMost read

From Gab Shop

Official merchandise. Every order funds free speech infrastructure.

Shop all products

Install Alto on your phone

Add Alto to your home screen for breaking news — no app store, no account.

  1. Step 1Open alto.gab.com in SafariMust be Safari — not Chrome or in-app browsers
  2. Step 2Tap the Share buttonSquare with an arrow, at the bottom of Safari
  3. Step 3Tap "More"If you don’t see Add to Home Screen yet
  4. Step 4Tap "Add to Home Screen"Scroll the share sheet if you need to
  5. Step 5Tap "Add"Alto appears on your home screen like any other app.
gab

Talk Markets Freely

Trade ideas, earnings, and the Fed with investors who aren't waiting on a moderator's approval.

What Makes Gab Different

We're not just another social network. We're a platform built on principles that matter.

Freedom of Speech & Reach

All First Amendment protected speech is welcome. No algorithmic throttling or shadow banning.

Family-Friendly Platform

We maintain a clean environment. Explicit adult content is strictly prohibited.

Western Nations Only

Third-world IPs are blocked. No scammers, no spam farms. Built for Western civilization.

Funded By Users

Our users are our investors and customers. You're not the product being sold.

Battle Tested

A decade of standing strong. Banned from app stores, banks—and still here.

American Owned & Operated

We reject foreign censorship demands. Built by Americans, for free people.

Support Alto & Gab

Alto is funded entirely by readers like you. Your donation helps us continue delivering curated news from a right-wing Christian Nationalist perspective, powered by Gab AI.